Background
 |
|
|
Marina Bay Financial Centre (MBFC) is being developed by a joint venture comprising three of Asia's most experienced and trusted property developers - Cheung Kong (Holdings) Ltd/Hutchison Whampoa, Hongkong Land and Keppel Land, and managed by Raffles Quay Asset Management (RQAM).
MBFC sits on a prime 3.55 hectare waterfront site at the heart of Singapore's new downtown. The tenant-centric design of this purpose-built financial centre combines the best in form and function, making it a key draw for businesses and befitting Singapore's position as a global financial hub.
MBFC offers a breathtaking blend of three distinguished office towers with nearly 3 million sq ft of Grade A office space, two residential towers comprising 649 luxury apartments and penthouses as well as approximately 176,000 sq ft of retail space to meet the daily convenience of our business community and residents.
MBFC achieved the Green Mark Gold for its office towers 1 & 2, Marina Bay Residences and Marina Bay Suites and the Green Mark Gold Plus for its office tower 3 conferred by the Building and Construction Authority of Singapore. This award recognises the efforts made by the developers to encourage sustainable design practices, and makes MBFC one of the few developments to win more than one BCA Green Mark award.
|
For further information, please contact:
Thomas Tan Director of Marketing, Residential
Rose Tong Director of Marketing, Retail
William Bright Director of Asset Management
Pauline Lim Senior Marketing Manager, Commercial
Tel : +(65) 6438 3328
Fax : +(65) 6438 3326
Email : enquiries@bfc.com.sg
|
|
|
Media Releases
Facts & Figures
Tower 1
Overall Size |
Approx. 57,600 sq. m NLA (Office Floors)
|
| Completion Date
|
2010 |
No. of Office Floor |
29 floors (3rd to 29th , 31st to 32nd )
|
Typical Floor Area |
Approx. 1,950 sq. m NLA |
Core to Window Depth |
Approx. 15.2m (N) / 13.4m (E) / 11.5m (S) / 13.4m (W)
|
Finished Floor-to-Ceiling Height |
2,750mm
|
Raised Floor |
Approx. 180mm from top of slab to top of raised floor
|
Planning Grid |
1,500mm
|
Floor Loading |
Office Floors: Live Load = 3.5 KN/sq. m ; Partitions = 1.0 KN/sq. m
|
Curtain Wall |
Unitised aluminium system with double glazed low E-solar tinted or single thermal toughened glass |
Total no. of Car Parking Spaces
|
Approx. 438 lots in both towers for tenant's use and approx. 248 lots at Central Park for the public
|
Toilets |
Male and Female, 1 Executive Toilet with shower combined with a Handicapped Toilet per floor
|
Pantry |
Provision for tenant's pantry exhaust connection to central pantry exhaust riser on every floor
Waste water discharge from Pantry to nearest waste stack by tenants. Alternatively, a floor standing waste water pumping unit is available in the market for connection by tenants subject to approval of waiver from PUB for use of unit.
|
Air-conditioning
|
24-hour chilled water supply from District Cooling System with an AHU per floor.
Estimated cooling load for a typical office floor is 240 kWr per floor.
One DCS chilled water tap-off points have been provided for each floor in conjunction with one supplementary chilled water tap off point which is backup by air-cooled chillers with emergency power supply for 20% of estimated cooling load
Two sets of chilled water riser pipes have been provided for each floor, subject to availability.
Space available for 3 nos tenants' own air-cooled chillers system, subject to availability
|
Security System |
24-hour CCTV monitoring at all main entrances and exits
Card Access Control via turnstiles to lift lobbies.
|
Fire Protection |
Addressable fire alarm system
Automatic sprinkler network, wet riser system, hosereels and portable fire extinguishers |
Lighting |
Average 500 lux at desktop level.
|
Incoming Electrical Supply & Electrical Loads |
Dual feed for 22 kV incoming power supply
Lighting: 15 W/sq. m
Power: 70 W/sq. m
|
Computer Earthing |
Provision of clean earthing available in each tenant data riser, subject to availability.
|
Standby Generator |
20% of estimated tenant normal load.
|
Spare Riser
|
For tenants' inter-floor cabling and specialised services
Total 6 nos risers (3 electrical risers & 3 data risers), subject to availability.
|
Space Reserved for Tenant's Own Generator
|
6 no. of generator spare plinths reserved for tenants' use, subject to availability
Provision of fuel pipe for connection to tenant's generator system.
|
Telecommunication |
Fibre Optic and telephone cabling in riser (by Service Provider) and MATV.
|
Lift Types |
Zone |
Number |
Load Capacity |
Speed |
Passenger Lifts |
Low rise:
1st, 3rd to 17th Storey
|
8 |
1,900kg (28 person) |
5m/sec |
Passenger Lifts |
High rise:
1st , 18th to 33rd Storey
|
8 |
1,900kg
(28 person) |
6m/sec |
Service Lifts |
All floors |
2 |
2,450kg |
3.5m/sec |
Carpark Lifts |
B2, B1 and 1st Storey |
2 |
900kg (13 person) |
1.5m/sec |
Tower 2
Overall Size |
Approx. 92,900 sq. m NLA (Office Floors) |
Completion Date |
2010 |
No. of Office Floor
|
43 floors (7th to 37th , 39th to 50th ) |
Typical Floor Area
|
Approx. 2,300 sq. m NLA |
Core to Window Depth |
Approx. 16.8m (N) / 15.8m (S) / 9.8m (E) / 9.9m (W) |
Finished Floor-to-Ceiling Height
|
2,750mm |
Raised Floor |
Approx. 180mm from top of slab to top of raised floor
|
Planning Grid |
1,500mm
|
Floor Loading |
Office Floors: Live Load = 3.5 KN/sq. m ; Partitions = 1.0 KN/sq. m
|
Curtain Wall |
Unitised aluminium system with double glazed low E-solar tinted or single thermal toughened glass
|
Total no. of Car Parking Spaces
|
Approx. 438 lots in both towers for tenant's use and approx. 248 lots at Central Park for the public
|
Toilets |
Male and Female, 1 Executive Toilet with shower combined with a Handicapped Toilet per floor.
|
Pantry
|
Provision for tenant's pantry exhaust connection to central pantry exhaust riser on every floor
Waste water discharge from Pantry to nearest waste stack by tenants. Alternatively, a floor standing waste water pumping unit is available in the market for connection by tenants subject to approval of waiver from PUB for use of unit.
|
Air-conditioning
|
24-hour chilled water supply from District Cooling System with an AHU per floor.
Estimated cooling load for a typical office floor is 290 kWr per floor.
Two DCS chilled water tap-off points have been provided for each floor in conjunction with two supplementary chilled water tap off points which are backup by air-cooled chillers with emergency power supply for 20% of estimated cooling load
Two sets of chilled water riser pipes have been provided for each floor, subject to availability.
Space available for 4 nos tenants' own air-cooled chillers system, subject to availability
|
Security System |
24-hour CCTV monitoring at all main entrances and exits
Card Access Control via turnstiles to lift lobbies.
|
Fire Protection |
Addressable fire alarm system
Automatic sprinkler network, wet riser system, hosereels and portable fire extinguishers
|
Lighting |
Average 500 lux at desktop level.
|
Incoming Electrical Supply & Electrical Loads |
Dual feed for 22 kV incoming power supply
Lighting: 15 W/sq. m
Power: 70 W/sq. m
|
Computer Earthing |
Provision of clean earthing available in each tenant data riser, subject to availability.
|
Standby Generator |
20% of estimated tenant normal load.
|
Spare Riser
|
For tenants' inter-floor cabling and specialised services
Total 8 nos risers (4 electrical risers & 4 data risers), subject to availability. |
Space Reserved for Tenant's Own Generator
|
8 no. of generator spare plinths reserved for tenants' use, subject to availability
Provision of fuel pipe for connection to tenant's generator system.
|
Telecommunication |
Fibre Optic and telephone cabling in riser (by Service Provider) and MATV.
|
Lift Types |
Zone |
Number |
Load Capacity |
Speed
|
Passenger Lifts |
Low rise:
1st , 7th to 22nd Storey
|
8 |
2,040kg
(30 person)
|
5m/sec |
Passenger Lifts |
Mid rise:
1st , 22nd to 37th Storey
|
8 |
2,040kg
(30 person) |
6m/sec |
Passenger Lifts |
High rise:
1st , 39th to 50th Storey
|
7 |
2,040kg
(30 person)
|
7m/sec |
Service Lifts |
All floors |
2
|
1,800kg |
5m/sec |
Carpark Lifts |
B2, B1, 1st to 6th Storey |
2 |
1,100kg
(15 person)
|
1.5m/sec |
Tower 3
Overall Size |
Approx. 114,700 sq. m NLA (Office Floors) |
Completion Date |
2012 |
No. of Office Floor
|
40 floors (5th & 6th, 8th to 38th, 40th to 46th) |
Typical Floor Area
|
Approx. 2,800 sq. m NLA |
Core to Window Depth |
Approx. 15.5m (N) / 14.3m (E) / 15.5m (S) / 14.0m (W) |
Finished Floor-to-Ceiling Height
|
Approx. 2,800mm |
Raised Floor |
Approx. 180mm from top of slab to top of raised floor
|
Planning Grid |
1,500mm
|
Floor Loading |
Office Floors: Live Load = 3.5 KN/sq. m ; Partitions = 1.0 KN/sq. m
|
Curtain Wall |
Unitised aluminium system with double glazed low E-solar tinted or single thermal toughened glass
|
Total no. of Car Parking Spaces
|
Approx. 354 lots for tenants
|
Toilets |
Male and Female, 1 Executive Toilet with shower combined with a Handicapped Toilet per floor
|
Pantry
|
Provision for tenant's pantry exhaust connection to central pantry exhaust riser on every floor
|
Air-conditioning
|
24-hour chilled water supply available from District Cooling System with two AHUs per floor
Estimated cooling load is approx.420 kWr per floor
Two DCS chilled water tap-off points have been provided for each floor in conjunction with two supplementary chilled water tap off points which are backup by air-cooled chillers with emergency power supply for 20% of estimated cooling load
Two sets of spare chilled water riser pipes have been provided on each floor, subject to availability
Space available for 6 nos. tenants' own air-cooled chillers system, subject to availability
|
Security System |
24-hour CCTV monitoring at all main entrances and exits.
Card Access Control via turnstiles to lift lobbies
|
Fire Protection |
Addressable alarm system
Automatic sprinkler network, wet riser system, hosereels and portable fire extinguishers
|
Lighting |
Average 500 lux at desktop level
|
Incoming Electrical Supply & Electrical Loads |
Dual feed for 22 kV incoming power supply
Lighting: 20 W/sq. m
Power: 65 W/sq. m
|
Computer Earthing |
Provision of clean earthing available in each tenant data riser, subject to availability
|
Standby Generator |
20% of estimated tenant normal load
|
Spare Riser
|
For tenants' inter-floor cabling and specialised services
Total 8 nos. risers (4 electrical risers & 4 data risers), subject to availability |
Space Reserved For Tenant's Own Generator
|
12 nos. spare plinths reserved for tenants' use, subject to availability
Provision of fuel pipe for connection to tenant's generator system
|
Telecommunication |
Fibre Optic and telephone cabling in riser (by Service Provider) and MATV
|
Lifts |
35 Passenger lifts in 5 lift zones with separate car park lifts (3 nos.) and service lifts (2 nos.)
|
|
|
|
|